Demolition complete on the second floor space. The masonry elevator shaft has been extended thru the roof and completed. The metal stud framing for all the corridor and tenant space walls is about 85% complete with electrical rough in work following. Wood blocking is being installed to accommodate the new tenant and corridor wood finishes. Eleven new skylights have been cut through the roof deck and installed. HVAC duct work and fire sprinkler piping is being installed in the ceiling spaces. The new structural steel for the stair extension from first floor to second floor is complete and wood blocking is being installed in the stairwell. Project status is about 35% complete.