Crow Peak Hall, Black Hills State University, Spearfish, SD 3/24/15

Crow Peak Hall, Black Hills State University, Spearfish, SD 3/24/15



Wing walls on the southeast side of the pedestrian bridge are complete and crews will now be moving to the northwest side.

Excavation has begun for the volleyball pit. DKC crews will begin installing volleyball poles, nets and boundary lines in conjunction with the sand placement.


Picture from the 4th floor of the building overlooking the BHSU campus and site activities. Work continues on the Amphitheater tiered concrete seating as well as the pedestrian bridge foundations and wing walls.   
 

Concrete terrace walls continue for the future amphitheater seating area.  


×